| SEGRO - Epsom |
 |
 |
| Demolition of existing glass works and construction of
six industrial units.
|
 |
| Contract Duration |
- |
30 weeks |
| Contract Basis |
- |
JCT Design & Build 2005 |
|
 |
| < BACK TO COMMERCIAL LIST |
|
|
 |
|
 |
|
“THIS WAS TALBOT’S SECOND PROJECT FOR SLOUGH ESTATES AND WOULD ORDINARILY HAVE BEEN A SIMPLE PROJECT. COMPLICATIONS INVOLVING EXTENSIVE ASBESTOS REMOVAL AND THE NEED TO COMPLY WITH STRICT ENVIRONMENTAL REQUIREMENTS WERE TAKEN IN OUR STRIDE AND THE PROJECT WAS SATISFACTORILY FINISHED ON SCHEDULE”
RICHARD BOWERMAN, CONTRACTS MANAGER
|
|
 |
|